Renovation and maintenance work within educational institutions

Latest News

Summer is the ideal time for renovation and maintenance work in school facilities. The total cost of the work carried out this summer for the 2022/2023 school year amounts to nearly โ‚ฌ12 million, distributed across a little over a hundred projects.

Maintenance and renovation work has been carried out over the past few months at Alphonse Daudet College, constructed in 1991, to provide students with a better environment in a few days.

The work carried out

Regarding the rehabilitation and renovation of the gymnasium and its locker rooms:

  • The tilework in the showers, the flooring, and the sanitary facilities were removed and replaced.
  • The walls were protected with high resistance PVC panels.
  • The paintwork was refreshed.
  • Additionally, the gym’s air treatment system was renovated.
  • Furthermore, inspection work was conducted on the gymnasium’s metal framework.

The library and the Agora hall also underwent a facelift with renovation and modernization:

  • The flooring and false ceiling tiles were removed and replaced.
  • The lighting was replaced with LED lights.
  • The paintwork was also refreshed.

The budget

  • The renovation of the locker rooms and gym passageways cost โ‚ฌ68,000.
  • The air treatment system cost โ‚ฌ272,000.
  • The framework inspection work cost โ‚ฌ57,000.
  • The library cost โ‚ฌ60,000.

For a total of approximately โ‚ฌ460,000 for the college’s work.